July 24, 2018
Overnight tomorrow, crews are now scheduled to line paint on the east side of Yonge Street between Gladman Avenue and Davis Drive, in Newmarket.
work dates*: Wednesday, July 25
work hours*: 7pm - 7am, overnight
what you need to know:
-
Overnight tomorrow, crews will pave, remove old traffic lines and paint lines on Yonge between Gladman and Davis.
-
Crews will shift the traffic to the west side of Yonge to start road widening works on the east side of the road between Gladman and Davis.
-
Northbound and southbound traffic will be reduced to one lane in each direction, within the work zone.
-
Traffic control staff and paid duty police officers will be on site to direct traffic.
-
There will be construction-related noise from equipment and trucks.
-
Expect delays, and please give yourself enough time to get to your destination, and remember to reduce your speed through construction zones.
crews dedicated to minimize disruption where possible:
-
Limit the reversing of vehicles with back-up safety beeper
-
Aim headlights away from buildings and homes
-
Reduce the banging noise from dump truck tailgates
-
Set up portable lights in a way that limits upcasting onto buildings
-
Ensure equipment is well maintained and running well
|
*Please note: As with all construction projects, some work may be re-scheduled due to weather. We’ll provide advanced notice when possible. Watch twitter.com/vivanext for last-minute updates.
We thank you for your patience while crews work quickly to complete this work. If you have any questions or concerns, please don’t hesitate to contact us.
Sophia Bittar | Community Liaison | 905.806.0713 | sophia.bittar@york.ca