September 13, 2018
As previously communicated, over the next few months, there will be several temporary side street road closures on the east and west sides of Yonge Street, from Davis Drive to Sawmill Valley Drive/Savage Road. These closures will accommodate a variety of work activities including road reconstruction, storm sewer installation, paving and line painting to support the future rapidway.
The third temporary side street road closures involve the entrances to Chapters/Pier 1 Imports/Starbucks [17440 Yonge] and Montana’s [17450 Yonge], and Newroads Subaru [17415 Yonge].
Visit vivanext.com/roadclosures for up-to-date information about scheduled road closures and to view detour maps.
work dates*: 7:00 pm on Friday, September 14 to 7am on Monday, September 17; with closures in place 24/7
what you need to know:
crews dedicated to minimize disruption where possible:
|
*Please note: As with all construction projects, some work may be rescheduled due to weather. We’ll provide advance notice when possible. Watch twitter.com/vivanext for last-minute updates.
We understand that overnight work is disruptive to those who live and work in the area, and have taken steps to reduce the impacts where possible. While we aim to balance the needs of commuters, businesses, area residents, the community at large and the project, night work is sometimes unavoidable. Read more about how we balance the needs of the corridor in our recent blog working day and night.
We thank you for your patience while crews work quickly to complete this work. If you have any questions or concerns, please don’t hesitate to contact us.
Sophia Bittar | Community Liaison | 905.806.0713 | sophia.bittar@york.ca